Duke Energy Carolinas medición neta en South Carolina

The Upstate and the northwest, including Greenville, Spartanburg, Anderson and Rock Hill. A separate South Carolina tariff from the same company’s North Carolina one. Do not carry a North Carolina figure across the state line.

Tipo
Compañía privada
Cuentas
600K

Cuánto le acreditan

Netted by time-of-use period; net excess at 4.19 cents

Condiciones publicadas

Rider RSC puts you on Schedule R-STOU, a solar time-of-use rate, and nets what you take against what you send within each pricing period of the month. Net excess energy in a period is credited at 4.19 cents a kWh under the sheet in force since 1 January 2026, against energy at 9.38 to 20.90 cents a kWh off-peak to on-peak before riders.

Mes a mes
Credits reduce that month’s bill after the minimum is applied.

Condiciones publicadas · verificado el 2026-10-08 · fuente

Instaladores que atienden a clientes de Duke Carolinas

Elija uno. Solo la empresa que usted elija recibe sus datos, y solo esa empresa le llama.

¿No sabe cuál elegir?

Estas son empresas reales que operan en el territorio de Duke Carolinas. Bold Energy aparece primero porque es la empresa que presentamos primero. Ese orden lo decidimos nosotros y no es una puntuación. Las demás empresas están ordenadas por reseñas, años de trayectoria y calificación BBB. Ninguna de ellas nos paga por su posición. Elija la que quiera y le llamaremos para organizarlo.

El orden combina tres cosas que leemos de fuentes primarias: el número de reseñas y la calificación de Google, los años de trayectoria tomados del perfil de la empresa en el Better Business Bureau y no de su propia publicidad, y su calificación por letra del BBB. La acreditación del BBB se muestra pero nunca se puntúa, porque es una membresía de pago y no una señal de calidad.

Verifique usted mismo la licencia de cualquier contratista en el registro estatal. Hágalo antes de firmar nada, con cualquier empresa, incluida la nuestra.

Cómo se ve esto en una factura de Duke Carolinas

Un hogar promedio de South Carolina, frente a un sistema dimensionado para cubrir su año. El cargo por energía es la parte que baja a cero. El cargo fijo mensual que hay debajo es la parte que nunca baja, y es la cifra que decide si un sistema se paga solo.

Lectura del medidorkWh
Cargo por energía$163.28
$163.28
Ya leímos la tarifa de esta compañía. Lo que le sigue cobrando con cero consumo aparece abajo, junto a la hoja de donde salió. La línea de energía de arriba usa el promedio estatal. Ver lo que le siguen cobrando
DirecciónLeyendo…

La lectura del medidor baja de 41926 a 41633 kilovatios hora. Un mes de 1,050 kilovatios hora frente a 1,343 kilovatios hora producidos deja 0 kilovatios hora facturados y 293 guardados para el próximo mes, así que el cargo por energía baja de $163.28 a $0.00 a 15.55 centavos por kilovatio hora.

Consumo promedio de un hogar en South Carolina, 1,050 kWh al mes, al precio residencial publicado actual de 15.55¢ por kWh. Su compañía sigue cobrando un cargo fijo mensual que ningún sistema elimina, así que esto es la parte de energía de la factura, que es la parte que desaparece.

Lo que su instalador debería estar diciéndole

The credit changes when Duke files a new sheet: 2.62 cents on the 2023 leaf, 4.19 cents since 1 January 2026, so check the leaf in force when you sign. The solar rate also carries a $0.47 per kW monthly non-bypassable charge, a $5.86 per kW grid access fee above 15 kW, and a $30 minimum on the customer and distribution charges that your credits cannot reduce. Systems are limited to 20 kW AC, and the renewable energy certificates go to Duke.

Las cifras de esta página están citadas de la tarifa de Duke Carolinas y de resoluciones estatales, publicadas únicamente en inglés. Las mostramos en el original en lugar de traducir una cifra legal y arriesgarnos a alterarla.

Lo que Duke Carolinas le cobra igualmente

En un mes en que su producción cubre todo lo que consume, el cargo por energía puede llegar a cero. Esto no. Es el mínimo de toda factura, y es la cifra que decide si un sistema se paga solo.

El cargo
$30.00 a month
Cómo se calcula
Rider RSC (SC), Residential Solar Choice, is the document that governs this, and it sets a rule rather than a number: the monthly minimum bill "shall be no less than the Basic Facilities Charge from the Customer’s rate schedule and riders plus, if applicable, any additional minimum bill provisions specified in the Customer’s rate schedule and riders." The figure that rule resolves to is $30.00, which the South Carolina Office of Regulatory Staff records for the Duke solar choice rates, with Duke Energy Carolinas customers paying an additional $16.91 above the basic facilities charge to reach it. The sentence that matters most is the next one in the rider: "Bill credits for net excess energy are not included in the calculation of the minimum bill charge. Bill credits will reduce a Customer’s total bill after the minimum bill charge has been applied." The minimum is worked out first and your solar credit is spent only on what is left, so no amount of export removes it. Three further conditions come with the rider and none of them are obvious from a quote: going on it moves you to Schedule R-STOU, a time-of-use rate, so the price of a kilowatt hour starts depending on when you use it; your system may not exceed 20 kW AC; and every environmental attribute, the renewable energy certificates included, is conveyed to Duke rather than kept by you. Exported energy is credited at 4.19 cents a kilowatt hour under the Third Revised Leaf No. 136, effective 1 January 2026 (the 2023 sheet said 2.62 cents). Schedule R-STOU, effective 2 October 2026, now words the floor as a Minimum Customer & Distribution Charge: when the Basic Customer Charge of $13.09, the customer and distribution portions of the energy charges and the volumetric riders come to less than $30, the difference is added, and the $0.47 per kW non-bypassable charge sits outside it.

Rider RSC (SC), Residential Solar Choice, South Carolina First Revised Leaf No. 136, effective for service rendered on and after 1 January 2023, PSCSC Docket 2020-264-E, Order 2021-390; the $30.00 figure from the SC Office of Regulatory Staff Solar Choice Rates Overview, as of 1 January 2022 · verificado el 2026-09-30 · fuente

Preguntas sobre la medición neta de Duke Carolinas

¿Ofrece Duke Carolinas medición neta uno por uno?
Sí. Rider RSC puts you on Schedule R-STOU, a solar time-of-use rate, and nets what you take against what you send within each pricing period of the month. Net excess energy in a period is credited at 4.19 cents a kWh under the sheet in force since 1 January 2026, against energy at 9.38 to 20.90 cents a kWh off-peak to on-peak before riders. Credits reduce that month’s bill after the minimum is applied.
¿Cuánto paga Duke Carolinas por la energía devuelta a la red?
Netted by time-of-use period; net excess at 4.19 cents.
¿Necesito una batería con Duke Carolinas?
No por las cuentas. Duke Carolinas acredita las exportaciones a la tarifa minorista, así que la energía que usted envía durante el día le vuelve con el mismo valor después del anochecer sin necesidad de almacenamiento. Una batería sigue mereciendo consideración por los apagones de la temporada de huracanes, pero aquí es una mejora y no un requisito.
¿Cómo encuentro mi factura de Duke Carolinas?
Sign in at duke-energy.com. Open My Account, then Billing & Payment. Open View Bill and save the PDF. Or screenshot the summary page. Si no consigue llegar a ella, un cálculo aproximado de su importe mensual promedio basta para empezar.
¿Cuál es la trampa con Duke Carolinas?
The credit changes when Duke files a new sheet: 2.62 cents on the 2023 leaf, 4.19 cents since 1 January 2026, so check the leaf in force when you sign. The solar rate also carries a $0.47 per kW monthly non-bypassable charge, a $5.86 per kW grid access fee above 15 kW, and a $30 minimum on the customer and distribution charges that your credits cannot reduce. Systems are limited to 20 kW AC, and the renewable energy certificates go to Duke.