Puget Sound Energy mezi nèt nan Washington

The central Puget Sound region, including Bellevue, Tacoma’s suburbs, Olympia and Bellingham. An investor owned utility, with net metering under its Schedule 150.

Kalite
Konpayi prive
Kont
1.2M

Konbyen yo kredite w

One for one in kWh, granted to PSE on 31 March

Kondisyon ki pibliye

Schedule 150 bills a month of net use normally. When the system sends more than the house takes, the excess kilowatt hours are credited and carried to offset consumption on following bills, one for one.

Mwa pa mwa
Excess kilowatt hours carry to following bills.
Yon fwa pa ane
On 31 March each year, any remaining unused kilowatt hour credits accumulated during the previous year are granted to PSE without compensation.

Kondisyon ki pibliye · tcheke 2026-10-07 · sous

Enstalatè k ap sèvi kliyan PSE yo

Chwazi youn. Se sèlman konpayi ou chwazi a ki resevwa enfòmasyon w yo, epi se sèlman konpayi sa a ki rele w.

Ou pa konn kiyès pou chwazi?

Sa yo se vrè konpayi kap travay nan zòn PSE la. Bold Energy parèt an premye paske se konpayi nou prezante an premye a. Se nou ki chwazi lòd sa a, se pa yon nòt. Lòt konpayi yo klase dapre avi, ane nan biznis ak nòt BBB. Okenn nan yo pa peye nou pou plas yo. Chwazi sa w vle a epi n ap rele w pou nou ranje sa.

Klasman an konbine twa bagay nou li nan sous prensipal: kantite avi ak nòt Google, konbyen ane nan biznis nou pran nan pwofil Better Business Bureau konpayi an olye nan piblisite pa l, ak nòt lèt BBB li a. Nou montre akreditasyon BBB la men nou pa janm bay li pwen, paske se yon manm ou peye pou li, se pa yon mak kalite.

Tcheke lisans nenpòt kontraktè ou menm nan rejis leta a. Fè sa anvan ou siyen anyen, ak nenpòt konpayi, menm ak pa nou an.

Kijan sa parèt sou yon fakti PSE

Yon kay mwayen nan Washington, kont yon sistèm ki gen gwosè pou kouvri ane a. Frè enèji a se pati ki desann rive zewo. Frè fiks chak mwa anba a se pati ki pa janm desann, epi se chif sa a ki deside si yon sistèm peye pou tèt li.

Lekti kontè akWh
Chaj pou kouran$142.39
$142.39
Nou li tarif konpayi sa a. Sa li toujou fè w peye ak zewo konsomasyon parèt pi ba a, ak fèy tarif kote li soti a. Liy kouran anwo a sèvi ak mwayèn eta a. Gade sa yo toujou fè w peye
DireksyonL ap li…

Lekti kontè a desann soti nan 41926 rive nan 41660 kilowat-è. Yon mwa 955 kilowat-è kont 1,221 kilowat-è pwodui kite 0 kilowat-è faktire ak 266 kenbe pou mwa pwochen, konsa chaj pou kouran an desann soti nan $142.39 rive nan $0.00 nan 14.91 santim pa kilowat-è.

Mwayèn konsomasyon yon kay nan Washington, 955 kWh pa mwa, nan pri rezidansyèl pibliye kounye a ki se 14.91¢ pa kWh. Konpayi ou an toujou chaje yon frè fiks chak mwa okenn sistèm pa retire, konsa sa se pati kouran an nan fakti a, ki se pati ki disparèt la.

Sa enstalatè w la ta dwe ap di w

Schedule 150 stays open to new applicants until 31 December 2025 or until a replacement net metering schedule is in place, whichever is later, and the sheet in force (9th Revision, effective 29 February 2024) names no replacement yet. Ask PSE which schedule your application will fall under. Meter aggregation carries a one-time $85 charge.

Chif ki sou paj sa a soti nan pwòp tarif PSE ak nan desizyon leta yo, ki pibliye sèlman an anglè. Nou montre yo jan yo ye olye nou tradui yon chif legal epi riske chanje l.

Sa PSE fè w peye kanmenm

Nan yon mwa kote pwodiksyon w kouvri tout sa w itilize, chaj enèji a ka rive zewo. Sa a pa rive zewo. Se plafon anba chak fakti, epi se chif ki deside si yon sistèm peye tèt li.

Chaj la
$7.49 a month
Kijan yo kalkile l
Schedule 7 sets a Basic Charge of $7.49 a month for single phase service, $17.99 for three phase, and states no separate minimum clause above it, so the basic charge is the floor. The sheet is banded by date and this is one of the rare cases where the band does not change the answer: it prints “Through January 28, 2026” and “Beginning January 29, 2026” and the Basic Charge is $7.49 in both. What moved was the energy, from 13.3017 cents to 14.1598 cents for the first 600 kilowatt hours and from 15.2434 to 16.1015 cents above that. The more useful thing here is what PSE does NOT do. Schedule 150, the net metering rider to schedules 7 through 49, says the rates for service through the designated meter “shall be equal to the basic charge in the schedule under which the Customer-Generator would normally receive service”. No extra monthly charge, no per kilowatt adder, no separate solar rate — a Washington customer-generator pays the same $7.49 as the neighbor without panels. That is unusual enough to be worth stating: Georgia, New York, the Carolinas, Alabama and both other Dakotas utilities all add something.

Schedule 7, Residential Service, 39th Revision of Sheet No. 7 and Original Sheet No. 7.1, WN U-60, Advice 2025-03, by authority of Order 09 in WUTC Dockets UE-240004 and UG-240005; net metering terms at Schedule 150, 9th Revision of Sheet No. 150, effective 29 February 2024 · tcheke 2026-09-30 · sous

Kesyon sou mezi nèt PSE

Èske PSE ofri mezi nèt youn pou youn?
Wi. Schedule 150 bills a month of net use normally. When the system sends more than the house takes, the excess kilowatt hours are credited and carried to offset consumption on following bills, one for one. Excess kilowatt hours carry to following bills.
Konbyen PSE peye pou kouran ou voye tounen nan rezo a?
One for one in kWh, granted to PSE on 31 March. On 31 March each year, any remaining unused kilowatt hour credits accumulated during the previous year are granted to PSE without compensation.
Èske m bezwen yon batri ak PSE?
Non, pa pou kalkil lajan an. PSE kredite kouran ou voye a nan to detay la, donk kouran ou voye pandan lajounen an retounen ak menm valè a apre solèy la kouche san ou pa bezwen depo. Yon batri toujou vo lapenn pou koupi kouran pandan sezon siklòn nan, men isit la se yon opsyon anplis, se pa yon egzijans.
Kijan pou m jwenn bòdwo PSE mwen an?
Sign in at pse.com. Open My Account, then Billing. Open the latest bill and save the PDF. Or screenshot the summary page. Si w pa ka jwenn li, yon estimasyon apeprè sou montan mwayèn ou chak mwa sifi pou kòmanse.
Ki pwoblèm ki gen ak PSE?
Schedule 150 stays open to new applicants until 31 December 2025 or until a replacement net metering schedule is in place, whichever is later, and the sheet in force (9th Revision, effective 29 February 2024) names no replacement yet. Ask PSE which schedule your application will fall under. Meter aggregation carries a one-time $85 charge.