Ale dirèk nan kontni an
Net Metering Program
← Retounen nan tablo a

Duke Energy Progress mezi nèt nan North Carolina

The east and the far west, including Raleigh, Wilmington, Fayetteville, Asheville and the Outer Banks. The former Progress Energy Carolinas. Same parent as Duke Energy Carolinas and the same rider names, but a lower export rate, a higher charge on your nameplate and a higher minimum bill.

Kalite
Konpayi prive
Kont
1.6M

Konbyen yo kredite w

Retail inside the month, a few cents outside it

Kondisyon ki pibliye

Rider NMB bills the net kilowatt hours supplied in the month, so exports offset what you buy at the full retail rate. Whatever is left over after that is bought at 3.94 cents, and a $28 minimum bill plus $1.16 per kilowatt of nameplate sits underneath the bill no matter what you generate.

Mwa pa mwa
Netting is monthly, not annual, so there is no bank to carry forward. Anything above your own monthly usage is settled at the Net Excess Energy Credit rate in the same bill.

Kondisyon ki pibliye · tcheke 2026-09-20 · sous

Enstalatè k ap sèvi kliyan Duke Progress yo

Chwazi youn. Se sèlman konpayi ou chwazi a ki resevwa enfòmasyon w yo, epi se sèlman konpayi sa a ki rele w.

Ou pa konn kiyès pou chwazi?

Sa yo se vrè konpayi kap travay nan zòn Duke Progress la. Bold Energy parèt an premye paske se konpayi nou prezante an premye a. Se nou ki chwazi lòd sa a, se pa yon nòt. Lòt konpayi yo klase dapre avi, ane nan biznis ak nòt BBB. Okenn nan yo pa peye nou pou plas yo. Chwazi sa w vle a epi n ap rele w pou nou ranje sa.

Klasman an konbine twa bagay nou li nan sous prensipal: kantite avi ak nòt Google, konbyen ane nan biznis nou pran nan pwofil Better Business Bureau konpayi an olye nan piblisite pa l, ak nòt lèt BBB li a. Nou montre akreditasyon BBB la men nou pa janm bay li pwen, paske se yon manm ou peye pou li, se pa yon mak kalite.

Tcheke lisans nenpòt kontraktè ou menm nan rejis leta a. Fè sa anvan ou siyen anyen, ak nenpòt konpayi, menm ak pa nou an.

Kijan sa parèt sou yon fakti Duke Progress

Yon kay mwayen nan North Carolina, kont yon sistèm ki gen gwosè pou kouvri ane a. Frè enèji a se pati ki desann rive zewo. Frè fiks chak mwa anba a se pati ki pa janm desann, epi se chif sa a ki deside si yon sistèm peye pou tèt li.

Lekti kontè akWh
Chaj pou kouran$149.61
$149.61
Nou li tarif konpayi sa a. Sa li toujou fè w peye ak zewo konsomasyon parèt pi ba a, ak fèy tarif kote li soti a. Liy kouran anwo a sèvi ak mwayèn eta a. Gade sa yo toujou fè w peye
DireksyonL ap li…

Lekti kontè a desann soti nan 41926 rive nan 41643 kilowat-è. Yon mwa 1,015 kilowat-è kont 1,298 kilowat-è pwodui kite 0 kilowat-è faktire ak 283 kenbe pou mwa pwochen, konsa chaj pou kouran an desann soti nan $149.61 rive nan $0.00 nan 14.74 santim pa kilowat-è.

Mwayèn konsomasyon yon kay nan North Carolina, 1,015 kWh pa mwa, nan pri rezidansyèl pibliye kounye a ki se 14.74¢ pa kWh. Konpayi ou an toujou chaje yon frè fiks chak mwa okenn sistèm pa retire, konsa sa se pati kouran an nan fakti a, ki se pati ki disparèt la.

Rider NMB is the one that nets your whole month against the retail rate, and it closes on 1 January 2027. Duke Progress must have a valid interconnection application in before then. It can also close sooner: new participation is capped each year and reserved first come, first served. After it closes the only rooftop option is Rider RSC, which forces you onto a time of use rate with critical peak pricing and nets each pricing period separately.

Sa enstalatè w la ta dwe ap di w

A $28 minimum bill and $1.16 for every kilowatt of nameplate sit under this bill every month, and your credits cannot touch either of them. Ask in writing which rider the quote assumes, because NMB and RSC produce different bills from the same array, and ask what you pay in a month when the energy nets to zero. Size the array to what the house uses rather than to what the roof holds: the kilowatt hours you use yourself are worth the retail rate, and the surplus beyond that is worth 3.94 cents.

Chif ki sou paj sa a soti nan pwòp tarif Duke Progress ak nan desizyon leta yo, ki pibliye sèlman an anglè. Nou montre yo jan yo ye olye nou tradui yon chif legal epi riske chanje l.

Sa Duke Progress fè w peye kanmenm

Nan yon mwa kote pwodiksyon w kouvri tout sa w itilize, chaj enèji a ka rive zewo. Sa a pa rive zewo. Se plafon anba chak fakti, epi se chif ki deside si yon sistèm peye tèt li.

Chaj la
$28.00 a month once you have solar, plus $1.16 for every kilowatt of panel
Kijan yo kalkile l
Schedule RES sets the Basic Customer Charge at $14.00 a month, with energy at 12.623 cents per kWh from May to September and 12.623 cents for the first 800 kWh from October to April. Riders NMB and RSC then set "a monthly minimum bill of $28 specific to the portion of the Customer’s bill related to customer and distribution costs", and state that "bill credits for net excess energy are not included in the calculation of the Minimum Bill Charge". Underneath that again is the Non-Bypassable Charge of $1.16 per month per kilowatt DC of nameplate. An 8 kW household whose energy nets to zero pays about $28.00 plus $9.28, roughly $37.28 a month or $447 a year. That is $88 a year more than the same house on the other Duke utility, for the same array.

Rider NMB, NC Fourth Revised Leaf No. 605, effective 1 April 2026, with Schedule RES, NC Second Revised Leaf No. 500 · tcheke 2026-09-20 · sous

Kesyon sou mezi nèt Duke Progress

Èske Duke Progress ofri mezi nèt youn pou youn?
Wi. Rider NMB bills the net kilowatt hours supplied in the month, so exports offset what you buy at the full retail rate. Whatever is left over after that is bought at 3.94 cents, and a $28 minimum bill plus $1.16 per kilowatt of nameplate sits underneath the bill no matter what you generate. Netting is monthly, not annual, so there is no bank to carry forward. Anything above your own monthly usage is settled at the Net Excess Energy Credit rate in the same bill.
Konbyen Duke Progress peye pou kouran ou voye tounen nan rezo a?
Retail inside the month, a few cents outside it.
Èske m bezwen yon batri ak Duke Progress?
Non, pa pou kalkil lajan an. Duke Progress kredite kouran ou voye a nan to detay la, donk kouran ou voye pandan lajounen an retounen ak menm valè a apre solèy la kouche san ou pa bezwen depo. Yon batri toujou vo lapenn pou koupi kouran pandan sezon siklòn nan, men isit la se yon opsyon anplis, se pa yon egzijans.
Kijan pou m jwenn bòdwo Duke Progress mwen an?
Sign in at duke-energy.com. Open My Account, then Billing & Payment. Open View Bill and save the PDF. Or screenshot the summary page. Si w pa ka jwenn li, yon estimasyon apeprè sou montan mwayèn ou chak mwa sifi pou kòmanse.
Èske gen yon dat limit pou kliyan Duke Progress yo?
Rider NMB is the one that nets your whole month against the retail rate, and it closes on 1 January 2027. Duke Progress must have a valid interconnection application in before then. It can also close sooner: new participation is capped each year and reserved first come, first served. After it closes the only rooftop option is Rider RSC, which forces you onto a time of use rate with critical peak pricing and nets each pricing period separately.
Ki pwoblèm ki gen ak Duke Progress?
A $28 minimum bill and $1.16 for every kilowatt of nameplate sit under this bill every month, and your credits cannot touch either of them. Ask in writing which rider the quote assumes, because NMB and RSC produce different bills from the same array, and ask what you pay in a month when the energy nets to zero. Size the array to what the house uses rather than to what the roof holds: the kilowatt hours you use yourself are worth the retail rate, and the surplus beyond that is worth 3.94 cents.